§ 205. Inversely Proportional Quantities

Consider the following problem: 6 workmen complete a certain job in 18 days. In how many days will 9 workmen complete the same job, working with the same efficiency as the first group?

This problem also concerns two quantities: the number of workmen and the duration of their work.

These quantities depend on one another, because when one changes, the other changes as well. However, this dependence is different from that in the problem in § 203.

There, when one quantity was increased by 2, 3, etc. times, the other quantity was increased by the same number of times.

Here, if the number of workmen is doubled, the duration of the same job is halved; conversely, if, for example, the number of workmen is reduced by a factor of three, the duration of the given job will, obviously, be increased by a factor of three.

If, when one of two quantities is increased (decreased) by a certain number of times, the other quantity is decreased (increased) by the same number of times, such two quantities are called inversely proportional.

Thus, the number of workmen and the duration of the given job are inversely proportional quantities.

Similarly: the weight of goods that can be purchased for a given sum of money (for example, 100 rubles) is inversely proportional to the price per unit of weight of these goods; the time taken to travel a given distance by a body moving uniformly is inversely proportional to the speed of motion; the value of a fraction with a constant numerator is inversely proportional to its denominator, and so on.

If one team has 6 workmen and another has 9 workmen, i.e., 96 = 112 times more, then the second team will complete the same job 112 times faster than the first, i.e.:

duration of work of 1st team / duration of work of 2nd team = number of workmen in 2nd team / number of workmen in 1st team = 112.

Thus, if two quantities are inversely proportional, the ratio of any two values of the first quantity is equal to the inverse ratio of the corresponding values of the second quantity.

Aurora and Freya — story illustration for § 205 “Inversely Proportional Quantities”
👨‍👩‍👧 In Plain Words (Kids & Parents)
Ask your child: Ask your child to demonstrate with numbers 12 and 4 on the right stage why the main rule of “Inversely Proportional Quantities” holds true.
Quick reference without leaving:

Study Guide for Parents, Teachers & Family Co-Learning — Lesson 205. Inversely Proportional Quantities

Core Idea in Plain Language

Inversely proportional quantities move in opposite directions: if one gets bigger, the other gets smaller by the same factor. For example, more workers mean less time needed to finish a job.

If, when one of two quantities is increased (decreased) by a certain number of times, the other quantity is decreased (increased) by the same number of times, such two quantities are called inversely proportional.
More workers mean fewer days needed.

Key Mathematical Terms:

Inversely proportionalRatioInverse ratioDuration of workNumber of workmen

Common Student Mistake & Socratic Fix

Typical pitfall: Billy looked at the problem where 6 workmen take 18 days and 9 workmen take 12 days. He tried to solve it using direct proportionality, setting up the ratio 6/9 = 18/x, and concluded that x = 27 days, thinking that more workmen should mean more days.

How to guide correction: Billy must remember that the number of workmen and the duration of work are inversely proportional. Therefore, the product of the number of workmen and the number of days remains constant. First, calculate the total work: 6 workmen × 18 days = 108 worker-days. Then, divide this total by the new number of workmen: 108 ÷ 9 = 12 days. The correct answer is 12 days.

Complete 4-Step Reasoning Walkthrough

  1. 1. Problem: 6 workers in 18 days6 → 18 days

    Aurora shows: six workers finish in eighteen days. If more workers join, time decreases. This is inverse dependence.

  2. 2. Compare workers: 9 to 69 / 6 = 1.5

    Freya calculates: nine workers is one and a half times six. Thus, work finishes 1.5× faster. Time decreases.

  3. 3. Calculate time: 18 ÷ 1.518 / 1.5 = 12

    Aurora divides eighteen by one and a half to get twelve. So, nine workers need twelve days. Check: 18 to 12 equals 9 to 6.

  4. 4. Conclusion: Inverse Ratio18/12 = 9/6

    Freya concludes: the ratio of days equals the inverse ratio of workers. This defines inverse proportionality.

Graded Practice Problems & Worked Solutions

  1. Problem 1 (§ 205). 6 workmen complete a job in 12 days. In how many days will 9 workmen complete the same job (inverse proportionality)?

    Hint: Use the fact that the product of the number of workmen and the number of days remains constant for the same amount of work. Set up the equation: (6 workmen × 12 days) = (9 workmen × x days).

    Worked solution: Calculate the total work units: 6 × 12 = 72 worker-days. Divide the total work units by the new number of workmen: 72 ÷ 9 = 8 days.
  2. Problem 2 (§ 205). At a speed of 4 km/h, a pedestrian covers a distance in 6 hours. In how many hours will he cover the same distance at a speed of 8 km/h?

    Hint: Recall that distance = speed × time, so for a fixed distance, speed and time are inversely proportional. Since the speed doubles from 4 km/h to 8 km/h, the time required should be halved.

    Worked solution: Calculate the total distance: 4 km/h × 6 h = 24 km. Divide the distance by the new speed: 24 km ÷ 8 km/h = 3 hours.
  3. Problem 3 (§ 205). By what factor will the work time decrease if the number of identical workmen is increased by a factor of 3?

    Hint: In inverse proportionality, the change in one quantity is the reciprocal of the change in the other. If the number of workmen is multiplied by 3, the time is divided by 3.

    Worked solution: Identify the relationship: Time ∝ 1 / Number of Workmen. Apply the factor: If workmen increase by 3, time decreases by a factor of 3.